Alberta's Major Projects registry lists the Blindman Industrial Park AI Data Centre in Red Deer County as Under Construction, with Havenz Smart Communities as the developer. majorprojects.alberta.ca
Red Deer County approved the data centre on October 7, 2025 — a 120-acre site with a 10,800 sq ft modular data centre and a 5,000 sq ft administration building on an on-site power plant. reddeeradvocate.com
The first hydrogen-ready reciprocating engines arrived in January 2026 with full construction underway; the first power module was targeted for commissioning in Q3 2026. rdnewsnow.com
Developed with Energy Haven and Indigenous equity partner Turning Stone. rdnewsnow.com
Its projects page lists AHI Red Deer as under construction on 119 titled acres, with a first 10 MW generation phase in commissioning. That is on-site generation, not IT load in service. havenz.ai
The Canada Investment Summit pitchbook, per BetaKit, lists the AHI AI Hub of Innovation scaling from 300 MW to one gigawatt and seeking equity — above any figure the company publishes. betakit.com
States that development permits are issued for the data centre and on-site energy centre, its AESO grid connection is at Stage 3, and 30 MW of firm gas supply is contracted. havenz.ai
Recent News
- Jan 26, 2026Expansion
Construction accelerates at AI data centre near Red Deer
Havenz Smart Communities, with Energy Haven and Indigenous equity partner Turning Stone, said the first hydrogen-ready reciprocating engines had arrived and full construction was underway at the AHI Hub of Innovation. The first power module remained on track for commissioning in the third quarter of 2026.
- Oct 7, 2025Government
Red Deer County approves data centre
Red Deer County approved an AI data centre in the Blindman Industrial Park north of Red Deer on a 120-acre site, comprising a nearly 10,800-square-foot modular data centre and a 5,000-square-foot administration building powered by an onsite heat and power plant.
People
Sourced from the company's own pages or announcements.
Sunny Sarpal
Chief Executive Officer
Technology Focus
Company site: havenz.aiTerms the company uses about its own work.
Similar Companies
Other companies in Cloud & Digital Infrastructure.